Tower construction Eastern span replacement of the San Francisco–Oakland Bay Bridge



march 4, 2011: phase 4 4 columns in place; jack-up crane (to left) used erect , dismantle scaffold, , gantry crane atop scaffold lifts , places tower columns.


the process build sas tower atop foundation consisted of 5 phases. first 4 phases each consisted of lifting 4 similar columns , bolting them place , elements connecting them, while last phase lift final top cap carry crowning main cable saddle. on july 28, 2010, first of 4 below-deck main tower pillars erected, having arrived earlier in month barge china. placed lifting 1 end barge temporary scaffold, carriage on barge allow lower end move place. after columns bolted place, scaffolding extended upward allow next set of above deck columns erected, lifted, , translated position, process repeated each of remaining phases.


tower erection continued when second set of columns arrived in week of october 24, 2010, 3 months after first set placed. second set of columns erected gantry atop scaffold , placed on first 4 columns placed earlier in year. after columns set place, bolted first set of columns. after second phase complete, tower 51 percent completed , stood @ height of 272 feet. third set of tower columns did not arrive until week of december 15, 2010. third set, larger crane, lifted , placed on second set of columns. tower stood @ impressive height of 374 feet , 71 percent complete. erection process did not continue until following year when final set of tower columns arrived valentine s day 2011. these 4 columns, each being 105.6 feet tall, lifted in week of february 28, 2011 , placed on third set of columns. tower stood @ height of 480 feet , 91 percent complete.



april 15, 2011: grillage in place.


the fifth , final tower phase lift grillage (a structure join columns, more commonly used foundation element) weighs 500 tons, lift main 450-ton cable saddle, , lift final tower head completed entire sas tower. of these final pieces arrived @ site same day fourth set of tower columns arrived. on april 15, 2011, first part of fifth , final phase began. 500-ton grillage lifted 500 feet in air , placed on fourth set of columns. tower stood @ height of 495 feet , 94 percent complete. took 1 day lift , place grillage on top of tower.